[04.09.2015]

Plan for Development and Operation for Maria approved

Olje- og energidepartementet har godkjent PUD'en for Maria-feltet i Norskehavet. Petoro har vært opptatt av god utnyttelse av eksisterende infrastruktur i forbindelse med Maria-utbyggingen.

Investments in the Maria development are estimated at around 15.3 billion NOK including development drilling. The planned production startup for Maria is in 2018. Recoverable reserves on the field are estimated around 180 million barrels of oil equivalent (boe), of which the majority is oil.

Under the approved development solution, the Maria reservoir will be linked via a subsea tieback to the Kristin, Heidrun and Åsgard B production platforms. The Maria well stream will go to the Kristin platform for processing while supply of water for injection into the reservoir will come from the Heidrun platform and lift gas will be provided from Åsgard B via the Tyrihans D field subsea template.

Processed oil will be shipped to the Åsgard field for storage and offloading to shuttle tankers. Gas will be exported via the Åsgard Transport System to Kårstø.

Wintershall Norge is the operator of the license with a 50%* share. Petoro has a 30% share and Centrica Resources (Norge) owns the remaining 20%.

*Subject to approval by the relevant authorities and after closing of the transaction by the end of 2015, Tellus Petroleum will acquire 15% of the Maria development from Wintershall. 

Flere nyheter

[07.08.2026] - Press release - First half 2026

Strong cash flow and key decisions for future production

[19.03.2026] - Press release Petoro annual results 2025

Secure deliveries in an uncertain world
Nyhetsarkiv